The ConnectUGA project formally began in July 2012 with training for staff directly involved with the process for implementing the new student information system powered by Banner. Over three years, project participants in the core areas of Undergraduate Admissions, Financial Aid, Registration and Records, and Student Accounts are working diligently to review business processes, streamline information and processes, and to support improved service to students and data-driven decision-making.
Key dates of the ConnectUGA project:
September 2013 – Admissions Go-Live (for Fall 2014 class)
March 2014 – Financial Aid Go-Live (all students)
March 2014 – Registration and Records Go-Live (all students)
July 2014 – Student Accounts Go-Live (all students)
September 2014 – June 2015 – Completion of Data Warehouse and Workflow Integration